Telestack Conveyor Helps Increase Production Volume & Efficiency
Location: Port Hedland WA
Machines: Telestack TC424X Tracked Conveyor
Material Type: Basalt
Bulk Density: 1.55m3
Stockpile Size: 20mm
The Telestack TC 424X Tracked Conveyor is one of the most versatile and useful stockpilers in the sector. The conveyor has helped thousands of mining and quarrying operations to literally move mountains. When one of our valued clients faced the issue of stunted production capacity, OPS was called in to help out. This is how we did it.
Problem:
Background:
Our client wanted an increase in production volumes and a stockpile capacity of -20mm crushed product. Their existing stacker limited production to around 250-275TPH.
Solution:
Increased production:
This enabled our client to increase plant production. As a result of incorporating the Telestack Conveyor, production achieved tonnages of around 325-350TPH. Far more efficient than the previous stacker machine.
Outcomes:
With the new TC424X on site, production capacity increased by ~78% (up from 250-275TPH to 325-350TPH).
The higher stockpile volume also allowed for more material crushing, without the need to move around. This meant less reliance on the conveyor to move material around.
The increase to production levels meant more efficient usage of the cone crusher. Higher stockpiles also meant the loader tailing out does not have to work as hard to keep up meaning a decrease in fuel and wear and tear on the GET.
At OPS we pride ourselves on helping clients increase the value of their operations.
READ MORE:
– We’ve recently saved a client nearly $1M by repairing their machine instead of replacing it.


Other Case Studies
Terex Finlay C1550 Cone Crusher | To Repair or Replace?
A Terex Finlay C1550 Cone Crusher came in with a failure which might have resulted in scrapping the unit. However, OPS rebuilt the chamber for approximately 19% of the cost of replacement.
A Mobile Plant Solution | Improving Goldmine Productivity
A mobile plant for a gold mining operation resulted in a faster, more efficient and productive business.
Mineral Processing Circuit Upgrade | OPS Consulting Case Study
A client's mineral processing circuit needed an upgrade in order to re-crush and screen existing stockpiles of already crushed Basalt. Their current equipment was not able to screen out all the required sizes.
Telestack Conveyor TC424X | Increasing Production Efficiency By 78%
The client was looking to increase production volumes and stockpile capacity but was limited by the existing stacker to around 250-275TPH.